Key Results
APC Project Guaranteed by Enero Solutions
+4,000 MW
+5 °C
-60 %
+98 % of Time
-55 % Process Variability
-76 % Process Variability
Challenges
Fluidized Bed Stability
Fluidized sand bed combustion technology offers high speed and strong responsiveness, enabling steam production to adapt efficiently to process demands. However, achieving this performance requires precise control of fluidization and bed temperature.
Energy and Operational Variability
The boiler recovers various grades of wood as well as off-gases from black pellet production, leading to significant variations in the fuel’s Lower Heating Value (LHV) that impact combustion. Compounding these fluctuations are variable export steam demands, which directly affect power generation.
Underutilized Cogeneration Potential
The combination of these factors constrained cogeneration performance, resulted in sub-optimal power generation, and risked non-compliance with GHG targets.